4: Laying the 9th course Wednesday PM
Francis using the remote control of the crane bringing down a palette of briques.

I am now convinced that the crane does speed up the job considerably.  All the blockwork and monomur could not have gone up so fast with only 2 men without it.

Rolling the glue onto the briques immediately before placing the next one - much quicker than laying concrete blockwork.

Some briques still have to be cut despite the 'prefabrication' .

The final boxes and contents for the temporary electricity supply, on Wednesday morning.

Next slide
 
Apr 18, 2007 - 03:37 PM
Friday morning - laying the lintel course. The leaves on the trees have come right out in the last week - compare with photos taken a week ago.

Lintel 'briques' ready for concrete to be poured around reinforcing.

Briques at window opening. The hole is for vertical reinforcing.

View of North West wall on Friday - complete to receive the floor beams on Tuesday when the concrete block retaining walls are up to the same level/.

Sliding the forks into a pallette of 'briques' - the crane is operated by the remote control on Francis' belt.

BluPlusPlus skin for JAlbum 5.1 created by Armond Avanes