BUILDING A SOLAR HOUSE IN FRANCE - WEEK 11 - Roofing »  Viewing imgp9897     [Image 13 of 30]  :: Jump To  
  First slide Previous slide      Index Page Start/Stop the slide show      Next slide Last slide  
Comment: By midday on Friday the North slope of the roof had been covered with roof sheeting ("ecran de toiture") which is waterproof but microperforated to allow the roof to breathe.
The floor joists under the mezzanine are oak, and will be dropped into the slots cut in the beams on the left. They are on the floor in the centre, being walked all over. I hope that it does not rain before the roof is covered, because oak shows black water marks that are hard to clean off.

Another job I had to do was to uncover the places where holes can be drilled through the concrete slab for pipes and other services.  I had placed blocks of polystyrene there before the slab was poured, where holes would miss reinforcing or precast beams.

Mr Mazieres and gang came back on Thursday and completed the rafters and fitted fascias.

In the afternoon they had framed the rooflight.  The crane lifted the posts and purlin, and held it all steady until the rafter were in place.  This is in fact a passive solar collector with vertical glazing which will also house the chimney of the wood stove, and a ventilator in summer.  There was much discussion about the precise position of the wood stove to get the elaborate flashing into position directly above it.

View from South of the frame of the roof light, which also gives light to the mezzanine.

Next slide
 
imgp9897.jpg - 2560 x 1920 - (3.26MB)
Oct 26, 2007 - 12:09 PM
The last half of the roof being covered on Friday afternoon.

When the sheeting was all held down to the rafters with small battens, the roof tile battens were marked out and nailed down.

Mr Mazieres working on the juction of the rooflight and the ridge. The whole was covered ready for the weekend.

Monday morning they started the tiling, having left it relatively watertight over the weekend.  The tiles are Terreal, type Canal Romane, colour Brun Rustique.

This will be short week because there is a public holiday on Thursday 1st November and nearly everybody takes a pont , Friday off to make a long weekend. So I am including work this week as part of week 11, which was also a short week as they did not work on Tuesday and Wednesday.

Album last updated on Nov 01, 2007 - 01:31 PM
Powered by JAlbum 6.5 and BluPlusPlus skin