BUILDING A SOLAR HOUSE IN FRANCE - week 16 - final windows and more interior »  Viewing imgp0227     [Image 1 of 16]  :: Jump To  
  You have reached the first slide You have reached the first slide      Index Page Start/Stop the slide show      Next slide Last slide  
Comment: At the end of December Mr Mazieres and his carpenters left without finishing the rest of the timber framing to receive larch cladding. At the end of January I decided to finish it myself as the rest of the windows are due to arrive next week and I want the house to be water tight and air tight.
Next slide
 
imgp0227.jpg - Feb 05, 2008 - 03:32 PM
Nailing on the battens over the microperforated sheeting. The boarding can't be nailed on until the 'auvent' (roof linking house and garage) is built because of flashings etc.

Interior view from kitchen direction showing the 'echelle de meunier' temporarily in postion to the mezzanine.

Monday 15th February - at last the windows arrived a day early.  There was a slight drama as the joiner had not phoned me to say he was coming and I arrived in the afternoon with a van load of Fermacell boards, and found some of the windows had been fitted incorrectly, and that the front door had been hung on the wrong side.

On Tuesday morning, a difficult meeting with Mr Dubuisson who agreed to correct the little errors of positioning , but tried to persuade us that the door would be better the way it was hung, but agreed that he should have phoned me before hanging it the opposite way to the drawings.  We agreed to think about it.

View of south corner.