To complicate matters on Monday, Francis Guinot phoned at 8:30 to say that he would be on site on half an hour.  We had been waiting for him or someone from Faye's since December to come to carry on with the external work and garage foundations and walls. In the meantime Francis had been elected Mayor of St Front la Rivière in the recent local elections.  So I despaired of ever seeing him personally on our project again, knowing how much work being Mayor of a commune involves.  But he arrived with his JCB to dig the holes for the septic tank and sand filter, closely followed by another gang from Faye to build the stone wall facing.

The new machine was finally made operational and plastering started after all the windows had been taped and covered.

Mr Maziere demonstrating to Benoit how to do it.  He then took over while Laurent did the skilled job of smoothing.


Albert about to give the machine its first cleanup.

Next slide
 
imgp0554.jpg - Apr 14, 2008 - 03:08 PM
The other gang from Faye began to build the foundation wall for the stone facing wall.

The cavity is filled with extruded polystyrene insulation (find me a waterproof ecological alternative)

A 3000 litre fosse toutes eaux was delivered on Monday afternoon, but I had to break the bad news that the regulations  required one of 4000 litres so it had to be taken back the next morning.

Comment: Francis began to dig the hole for the septic tank (in this case a "fosse toutes eaux" which takes all soil and waste water).