week 39 - electricians and plumbers - lighting and solar water heater started

imgp8823
15th January. The 1000 litre hot water storage and buffer tank for the underfloor heating. with its insulating jacket.

15th January. The 1000 litre hot water storage and buffer tank for the underfloor heating. with its insulating jacket.
imgp8829
The Siemens system for controlling the temperature of the water to the underfloor heating coils.

The Siemens system for controlling the temperature of the water to the underfloor heating coils.
imgp8837
The solar panels for the domestic hot water system (Giordano)

The solar panels for the domestic hot water system (Giordano)
imgp8838
This week in early January the heating system was tested each day while I was working on the chestnut floors and poplar ceilings. The Godin had no difficulty in producing enough heat (more than I anticipated going up the chimney !). But 1000 lires of water took about 6 hours to start producing water hot enough the few radiators. I suggested to the plumber an optional by-pass direct to the radiators, which he put in.

This week in early January the heating system was tested each day while I was working on the chestnut floors and poplar ceilings. The Godin had no difficulty in producing enough heat (more than I anticipated going up the chimney !). But 1000 lires of water took about 6 hours to start producing water hot enough the few radiators. I suggested to the plumber an optional by-pass direct to the radiators, which he put in.
imgp8841
The back of the Godin - later to be enclosed. Air supply to the fire is ducted from the basement.

The back of the Godin - later to be enclosed. Air supply to the fire is ducted from the basement.
imgp8840
Laying the floor in the bathroom. The boarding is acacia (robinia) an extremely hard and completely rot-proof timber which grows in profusion locally.

Laying the floor in the bathroom. The boarding is acacia (robinia) an extremely hard and completely rot-proof timber which grows in profusion locally.
imgp8843
The acacia floor in the bathrooom.

The acacia floor in the bathrooom.
imgp8854
Poplar ceiling in the bathroom with LED spots.

Poplar ceiling in the bathroom with LED spots.
imgp8846
The heat recovery ventilation system (VMC double-flux) installed in the roof space. This extracts air from kitchen and bathrooms and distributes air to the living and bedroom spaces after going through a heat exchanger to warm it. It is remotely radio controlled from anywhere in the house. For this to be effective the house must be highly insulated and very airtight in winter. This is the system called 'Passiv Haus' in Germany, and when there is enough solar gain through south facing windows it eliminates the need for any supplementary heating. But modelling with SPIEL shows that during very cold grey periods, the Godin wood burner will be needed.

The heat recovery ventilation system (VMC double-flux) installed in the roof space. This extracts air from kitchen and bathrooms and distributes air to the living and bedroom spaces after going through a heat exchanger to warm it. It is remotely radio controlled from anywhere in the house. For this to be effective the house must be highly insulated and very airtight in winter. This is the system called 'Passiv Haus' in Germany, and when there is enough solar gain through south facing windows it eliminates the need for any supplementary heating. But modelling with SPIEL shows that during very cold grey periods, the Godin wood burner will be needed.
imgp8839
The 300 litre tank for the Giordano solar heating being installed in the mezzanine bedroom cupboard.

The 300 litre tank for the Giordano solar heating being installed in the mezzanine bedroom cupboard.
imgp8850
The domestic hot water tank in place.

The domestic hot water tank in place.
imgp8851
The Giordano solar control unit with display showing temperatures in the the collector and bottom of the tank.

The Giordano solar control unit with display showing temperatures in the the collector and bottom of the tank.