Week 4 began after a delay of 4 months - christmas and new year, then waiting for the monomur briques to be made and delivered, took us to mid February, but then Francis Guinot got involved in another job that had complications, we went to UK for a week, and agreed a resumption of work in March. But sorting out the other job took longer than anticipated and finally we extracted a promise to be back on site straight after Easter. On Tuesday, Francis phoned to say that he was bringing a crane onto the site to speed up moving materials. But he said that ideally he needed a 3 phase electricity supply.