BUILDING A SOLAR HOUSE IN FRANCE - WEEK 27 - Underfloor heating pipes, screeds »  Viewing imgp0924     [Image 11 of 17]  :: Jump To  
  First slide Previous slide      Index Page Start/Stop the slide show      Next slide Last slide  
Comment: The 4 circuits in the living space.
Michel fixing the distribution connection for the underfloor heating.  There are 5 circuits each with taps and balancing valve.

After all the circuits are fixed they are filled with water and 'inflated' under pressure using this hand pump.

The circuit under the stair.

The next day Mr Augustin and his little gang arrived to do the screeds.

The screed being laid in the sous sol shower room and laundry.

The finished levelling screed over the hemp and lime insulating screed, which could not be finished smooth enough  to receive tiles.

While Mr Augustin did the screed downstairs, we cleared up and prepared the edge formwork for the screed.

The temporary stair (echelle de meunier) to the mezzanine had to be removed and temporarily fixed to go down to the sous sol.

Next slide
 
Jul 10, 2008 - 12:28 PM
On the days that Margaret and I work all day on site we take our lunch break in Brantome - a workers lunch - omelette and glass of wine.

First a very liquid cement/sand slurry with something added to encase the pipes is spread - here in the kitchen.

Mr Augustin and his men.

The fluid enrobing slurry being laid in the living area.  That was left to set over a weekend and then they came back to lay the final dry screed on Tuesday.

Before the final dry sand/cement screed is laid a steel reinforcing grille is laid on top of the dry enrobing screed/

The screed finishes very dark grey which is closer to the final colour of the slate tile floor.

Album last updated on Aug 15, 2008 - 09:54 PM
Powered by JAlbum 6.5 and BluPlusPlus skin