Building a solar House in France - partitions and sanding oak frame etc. »  Viewing imgp0879     [Image 11 of 14]  :: Jump To  
  First slide Previous slide      Index Page Start/Stop the slide show      Next slide Last slide  
Comment: The connector for the underfloor heating pipes.
I kept out of the way by working on the roof, putting linseed on the woodwork of the roof light boarding.

By 5 pm Michel and apprentice had nearly finished but were short of a few boards and went away for a few days to wait for a delivery.

The back of the Godin 'insert' wood burner.  It has a 15 kw back boiler which will heat water in a 1000 litre tank, which in turn will supply the heat for the low temperature underfloor heating, and a few radiators.

The insulation boards start to make the interior look more finished.

Living area looking towards the fire which will be flush with a wall made of heat storing blocks with tiling surround.

Next slide
 
Jul 02, 2008 - 10:48 AM
While the ground floor is cleared for action the workshop moves up to the mezzanine to finsih the 'fermacell' wall panels.

The kitchen ceiling nearly finished leaving the ceiling light slot.

In the sous sol, all the interior cills of the glazed doors have to have an insulating screed.

Album last updated on Aug 15, 2008 - 09:49 PM
Powered by JAlbum 6.5 and BluPlusPlus skin