Comment: While the ground floor is cleared for action the workshop moves up to the mezzanine to finsih the 'fermacell' wall panels.
By 5 pm Michel and apprentice had nearly finished but were short of a few boards and went away for a few days to wait for a delivery.

The back of the Godin 'insert' wood burner.  It has a 15 kw back boiler which will heat water in a 1000 litre tank, which in turn will supply the heat for the low temperature underfloor heating, and a few radiators.

The insulation boards start to make the interior look more finished.

Living area looking towards the fire which will be flush with a wall made of heat storing blocks with tiling surround.

The connector for the underfloor heating pipes.

Next slide
 
Jul 02, 2008 - 10:52 AM
The kitchen ceiling nearly finished leaving the ceiling light slot.

In the sous sol, all the interior cills of the glazed doors have to have an insulating screed.